Back to Journal

Architectural Editorial

CHB Need-Based Changes in Chandigarh: 2026 Rules, Fees and Forms

Planning a change to a CHB flat or house in Chandigarh? See which need-based changes the March 2026 order implements, the fee for each, the forms CHB asks for and what is still pending.

AI-enhanced interpretation of the Arcadia courtyard photograph, with warm daylight and green planting
Arcadia · Residence · Wave Estate, Mohali View project AI-enhanced image based on the Arcadia project photograph (Mohali). View the project for original photography.

In short

  • CHB’s 10 March 2026 order implements need-based change clauses 1–21, 24 and 26–28; it does not apply to CHB units in Chandigarh Phase I.
  • A rear courtyard or terrace can be covered up to 150 sq ft or 75%, whichever is less, at ₹200/sq ft + GST (minimum ₹20,000); independent houses are excluded.
  • File Forms A or B with the architect’s Form D and a structural stability certificate; proposed work can start 30 days after a complete application if CHB raises no objection.
  • The Delhi-model regularisation on the CHB board’s 3 November 2026 agenda is a proposal, not approved policy.

This is a general overview of CHB’s published need-based changes framework as of 31 October 2026. The position for a particular unit depends on its scheme, phase and records.

Contents

What “need-based changes” means

Chandigarh Housing Board (CHB) dwelling units were built to a fixed design. Over the years many owners have added a room at the back, enclosed a balcony or put a grill on it. CHB’s need-based changes policy lists the additions and alterations it allows, each with its own conditions and fee, so owners can apply for them instead of living with an unapproved change.

This guide is for owners of CHB flats and houses who want to make, or regularise, a change. It reflects the published orders as of 31 October 2026. It is not an approval for any particular unit; confirm the position for your own home with CHB before building.

Which order applies now

The policy is CHB’s Order No. 02 of 3 January 2023, which lists 28 changes. CHB order, 3 Jan 2023

On 10 March 2026, after a high-powered committee reviewed the order in the light of the Supreme Court’s January 2023 judgment, CHB directed that clauses 1–21, 24 and 26–28 be implemented. Two conditions matter:

  • It is not applicable to CHB dwelling units in Chandigarh Phase I.
  • For clause 1 (balconies), the curtailed balcony is to be specified property type and scheme wise.

CHB implementation order, 10 Mar 2026

Clauses 22, 23 and 25 were not included. News reports from February 2026 listed the clauses differently; where a news summary and the signed order disagree, rely on the signed order.

Why the limits are tight

In January 2023 the Supreme Court directed that the Centre and the Chandigarh Administration freeze FAR and not increase it further. The 2026 committee treated that direction as prospective. It is why the policy works through a fixed list of changes rather than open permission to add floor area. Supreme Court judgment, 10 Jan 2023

Every implemented change, with its fee

Fees are as published by CHB and are plus GST. “Structural certificate” means a structural stability certificate on CHB’s standard proforma (Annexure-A1) from a structural engineer on the Chandigarh Administration’s panel.

ClauseChangeFeeMain conditions
1Balcony of 914 mm (3 ft) on the front or rear courtyard, where none was provided₹10,000Structural certificate; shorter width where a neighbour’s privacy is affected; not on a façade that already has a balcony or verandah
2Chhajja over doors and windows₹5,000 per unit if not to the standard designProjection no more than 1’-6”; not over government land
3Extra window in the end wall of a corner unit₹200 per standard drawing print (free online)Size and position as per CHB’s drawings
4Lowering a window sillNone statedDown to 4 inches above floor level
5Additional construction shown in CHB’s type-wise drawings₹200 per sq ftConsent of the owner of the adjoining floor; structural certificate
6Removing wallsNone stated115 mm (4½ inch) internal walls in flats; thicker walls only in independent houses, with a structural certificate
7Grill or glazing on a balcony or verandah₹10,000 per balcony (grill); ₹25,000 per balcony (glazing)A 4 ft × 4 ft area must open for fire rescue; clearance from the Chief Fire Officer
81 m × 1 m cut-out in the roof slab for servicesNone statedIn the common area, covered with a flap door
9Wider main gateNone statedUp to 12 ft wide and 6 ft high
10Exterior paint and tilesNone statedUniform colours for each block; tiles only on the flat’s main entry façade
11Temporary car shedNone statedSteel pipe frame with transparent polycarbonate or fibreglass, inside the boundary wall, average height up to 7’-6”
12Lightweight sunshades over balconiesNone statedAs per the standard design
13Internal changesNone statedStructural certificate; plans certified by a panel architect (Form D); no added covered area; no change to the exterior
14One additional doorNone statedStructural certificate before work; not opening onto public or green space
15Room over the rear courtyard or terrace₹200 per sq ft, minimum ₹20,000See the next section
1610 ft gate in the rear courtyard wallNone statedOnly on V-5 and V-6 roads; grill on that wall up to 2’-3”
17Covering the corridor, HIG (Upper), Sector 45-A₹10,000Consent of every allottee in the block; structural certificate
18Moving the gate from the side wall to the front wall₹5,000 per unitNo CHB approval needed; the road berm must be a ramp without steps
19Using the parking roof as a terrace (specified HIG types, Sectors 45-A and 39-B)₹5,000 per unitConsent of the upper-floor owners; railing only, no covering
20LiftNone statedDesign approved through OBPAS by an empanelled private architect; CHB NOC after a 15-day notice to the block
21Covering voids, HIG (Lower) Cat-II, Sectors 47-C, 45-B, 41 and 38-A₹15,000 for the store above the scooter parkingThe ducts themselves cannot be covered
24Rainwater spouts joined to one pipe or to rainwater harvestingNone statedServices kept off the street face where possible
26Foldable shades over end-wall windowsNone statedUp to 1’-6” wide
27Bigger water tankNone statedUp to 1,000 litres; structural certificate
28LIG (Upper) duplexes, Sector 41-A: room widened about 2 ft into the rear courtyard, first-floor terrace as a glass house, second-floor terrace garden₹200 per sq ft, minimum ₹20,000 (room)The widened area counts against the clause 15 limit

Sources: CHB order, 3 Jan 2023 and the fee checklists in Forms A and B of the CHB SOP.

The rear room: clause 15 in detail

This is the change most owners ask about. Clause 15 allows additional construction of 150 sq ft or 75% of the rear courtyard or terrace, whichever is less, in CHB dwelling units except independent houses. The conditions are:

  • Light and ventilation as required by condition 4.2.11 of the Chandigarh Building Rules (Urban), 2017.
  • Plans prepared and submitted by a private architect on the Chandigarh Administration’s panel for self-certification.
  • A structural certificate.
  • The roof of the new room must be non-accessible, with a 9-inch parapet, and nothing may be built on it.
  • The room’s clear height is the same as the unit’s habitable rooms.
  • A fee of ₹200 per sq ft + GST, minimum ₹20,000 + GST.
  • An owner who occupies more than one floor can use this benefit on one floor only.

Rooftop solar: no NOC needed

Clause 25 of the 2023 order needed the consent of every allottee in the block. CHB’s 13 October 2026 order replaces that: allottees may install rooftop solar strictly within the guidelines of the PM Surya Ghar: Muft Bijli Yojana through CREST, and no prior approval or NOC from CHB is required. CHB solar order, 13 Oct 2026

How to apply

CHB’s standard operating procedure sets out the file. CHB SOP

  • Form A if the change already exists and you want it regularised.
  • Form B if you propose to build it.
  • Form D, the architect’s self-certification of the plans, where the clause needs certified plans (for example clauses 13, 15 and 28).
  • Form E, mutual consent, where other owners must agree.
  • Annexure-A1, the structural stability certificate.
  • The fee for each change.

The application is handed in at CHB’s reception counter, which accepts only complete files, and is examined by the Architect, CHB. CHB relies on the documents as submitted; responsibility for their correctness lies with the architect, the structural engineer and the applicant.

For new work, construction may start only 30 days after a complete application, and only if CHB has raised no objection.

Who signs the drawings

CHB’s Form D is signed by an architect registered with the Council of Architecture who states that they are empanelled with the Chandigarh Administration for self-certification. Separately, the Administration’s July 2020 notification made COA-registered architects eligible for ordinary building plans without separate empanelment. Because CHB’s own form still uses the word “empanelled”, confirm with CHB what it accepts before you appoint anyone. Chandigarh notification, 20 Jul 2020

What is still pending

On 27 October 2026, The Tribune reported that the CHB board would consider a wider, Delhi-model regularisation of need-based changes at its meeting on 3 November 2026, and that planners had objected to backyard rooms. The Tribune, 27 Oct 2026 We had not found a report of the outcome when this was last checked on 5 November 2026, so treat it as undecided until CHB publishes an order.

That proposal is not approved policy. Until CHB issues a written order, plan on the basis of the March 2026 order and the SOP. We will update this guide when a decision is published.

Five mistakes to avoid

Relying on a news list. Clause numbers in news reports have not always matched the signed order.

Assuming Phase I is covered. The March 2026 implementation order excludes CHB units in Chandigarh Phase I.

Treating a house like a flat. The clause 15 rear room excludes independent houses, and the whole policy applies to CHB dwelling units only. Private kothis on Estate Office plots follow the Chandigarh Building Rules instead.

Building before the clock runs out. For new work, wait 30 days from a complete application.

Glazing without a rescue opening. Without the 4 ft × 4 ft openable area and the fire officer’s clearance, glazing does not meet the conditions.

What to prepare before you meet an architect

  1. Your unit: the CHB scheme, sector, phase, category, floor and dwelling unit number, and your allotment papers.
  2. What exists today: photos and rough measurements of any change already made, and when it was made.
  3. What you want: the room, cover, grill, glazing or lift you have in mind, and how you will use it.
  4. Other owners: whether the change touches a shared wall, terrace, corridor or staircase, in which case their consent may be needed.
  5. Open questions: anything CHB has told you, any notice you have received, and whether the work is for your own use or ahead of a sale.

Discuss your CHB change with the studio

Ajooni Jasleen Architects designs homes and interiors in Chandigarh and Mohali. Tell the studio about your unit, the change you want and the records you have, and it can discuss design options and the drawings your file needs. Confirm with CHB who is eligible to certify the file under its current forms.

Discuss your change.

Building on a GMADA plot in Mohali instead? Read our GMADA building approval guide.

Sources

  1. CHB — Need-based changes order, 3 January 2023 The policy text: permitted changes, conditions and fees, including the grill and glazing charges. chbonline.in
  2. CHB — Implementation order, 10 March 2026 Implements clauses 1–21, 24 and 26–28; not applicable to CHB units in Chandigarh Phase I. chbonline.in
  3. CHB — Standard operating procedure, 2026 Forms A, B, D and E, structural stability, fees and the 30-day start rule. chbonline.in
  4. CHB — Rooftop solar order, 13 October 2026 Rooftop solar under PM Surya Ghar / CREST guidelines without prior CHB approval or NOC. chbonline.in
  5. Supreme Court of India — Judgment, 10 January 2023 Directs that FAR in Chandigarh is not increased further. sci.gov.in
  6. Chandigarh Administration — Notification, 20 July 2020 COA-registered architects eligible for building plans without separate empanelment. chandigarh.gov.in
  7. The Tribune — CHB board to consider Delhi model, 27 October 2026 News report of the 3 November 2026 board discussion; not an approved policy. tribuneindia.com

This guide is a general overview, not legal advice. Confirm the current order, fees and certification requirements for your unit with Chandigarh Housing Board before building.

Chandigarh CHB homes

Discuss Your CHB Change

Tell the studio about your CHB unit, the change you want and the records you have. Ajooni Jasleen Architects can discuss design options and the drawings your file needs.

Studio
E-37, AADH Towers, Phase-8, Industrial Area, Mohali

Enquire Now